A 12,500 square foot Tuesday Morning shell and tenant finish project is well under way in Colorado Springs at Powers Pointe.
DPGA provided full scope services on an accelerated schedule. From design start, through entitlements and permit, and ultimately construction, the project will be completed and turned over to the tenant in 8-1/2 months. Every day counts, so construction documents were completed in less than four weeks….and they had to be accurate and thorough. Jurisdiction plan review was complete in just over 30 days, and the tenant approved the plans on the first review. CSI Construction Company is hard at work keeping the build schedule on target.
Additional buildings are in the works at Powers Pointe, and we are eager to build on the success of this turnkey deal.